ENGINEER'S OPINION OF PROBABLE COST
Project: AIR PARK Date: 15-Apr-04
Location: Fort Collins Job No.: 17489
Subject: Estimated Probable Cost Prep. By: J. White
Client: LLoyd Goff Ckd. By: J. Moore
           
Note: Any opinions of price, probable project costs or construction costs rendered by MARTIN/MARTIN represent
its best judgment and are furnished for general guidance.  MARTIN/MARTIN makes no warranty of guarantee,
either expressed or implied as to the accuracy of such opinions as compared to bid or actual cost.
Item No. Item Description Units Quantity Unit Price Item Cost
  PRE-CONSTRUCTION          
  Mobilization ea. 1  $      2,000.00  $         2,000.00
  Clearing and Grubbing / Acre 150  $         450.00  $       67,500.00
  Topsoil - (Removal  6", Stock Pile) / cu. yd. 36850  $            1.75  $       64,487.50
             
  SEDIMENT CONTROL          
  Sediment Containment System ea. 1  $      1,500.00  $         1,500.00
  Standard BMP's (silt fence, washout, VTC) L.S. 1  $    10,500.00  $       10,500.00
             
  EARTHWORK          
  Earthwork - Overlot Grading / cu. yd. 503,200  $            1.50  $     754,800.00
             
  DRY CREEK CHANNEL          
  Dry Creek Channel Improvements L.S. 1  $  240,000.00  $     240,000.00
  10' Maintenance Trail (concrete) / lf. 6800  $          25.00  $     170,000.00
  Twin 5ft by 10ft Box Culvert L.S. 1  $  265,000.00  $     265,000.00
  Storm Sewer Diversion (50 cfs) L.S. 1  $    75,000.00  $       75,000.00
             
  ROADWAY SECTION ON-SITE          
  Sanitary Sewer / lf. 6000  $          50.00  $     300,000.00
  Storm Sewer / lf. 6000  $          75.00  $     450,000.00
  Water Main / lf. 6000  $          50.00  $     300,000.00
  Subgrade Prep / sy. yd. 45200  $            1.50  $       67,800.00
  Curb and Gutter / lf. 22300  $          11.00  $     245,300.00
  12" Full Depth Asphalt Section / Tn. 24650  $          42.00  $  1,035,300.00
  6' Sidewalk (both sides) / lf. 12000  $          15.00  $     180,000.00
  Landscape Center Median / sy. yd. 11700  $          27.00  $     315,900.00
  Landscape adjacent to ROW / sy. yd. 13300  $          27.00  $     359,100.00
  Signalization--2 L.S. 1  $  240,000.00  $     240,000.00
           
  ROADWAY SECTION OFF-SITE          
  Subgrade Prep / sy. yd. 12700  $            1.50  $       19,050.00
  Curb and Gutter / lf. 7150  $          11.00  $       78,650.00
  12" Full Depth Asphalt Section / Tn. 7330  $          42.00  $     307,860.00
  6' Sidewalk (both sides) / lf. 3570  $          15.00  $       53,550.00
  Landscape Center Median / sy. yd. 3800  $          27.00  $     102,600.00
  Landscape at ROW / sy. yd. 4000  $          27.00  $     108,000.00
         
Remarks:   Cost of Items:  $  5,813,897.50
    15%  Contingencies:  $     872,084.63
    Subtotal:  $  6,685,982.13
  15%   Const. Engineering/Observation:  $  1,002,897.32
         
        Total Cost:   $  7,688,879.44