Document |
Description |
Date |
Format |
|
|
|
|
|
|
Greeley Water |
Greeley has purchased a 40' Right-of-Way for $268,000 for a
Water Line |
11-15-08 |
PDF |
|
Lawsuit |
The lawsuit over easement access by off site aircraft was
dismissed |
11-05-08 |
PDF |
|
MOCA |
The landowners Association has engaged an experienced metro
District manager |
11-01-08 |
PDF |
|
Refinance |
Mile High bank has extended the loan to 2-15-09 |
9-15-08 |
PDF |
|
Metro District |
The City issued standards for Metro District applications |
7-09-08 |
PDF |
|
Appraisal |
The property appraised for $16,975,000 by Coldell Banker
Richard Ellis |
6-25-08 |
PDF |
|
ODP
Plan |
Approved overall development plan slide
show |
|
|
|
ODP Approval |
The City has approved the Overall Development Plan |
4-18-08 |
PDF |
|
Contamination NFA |
The State of Colorado has issues a "No Further Action"
required letter |
4-15-08 |
PDF |
|
Flood Channel |
The City has presented their final design to Airpark Village |
3-04-08 |
PDF |