2.0 METHODOLOGY
On October 18, 2005, Stewart Environmental met with local utility companies to
identify existing onsite utilities. Identification of such locations is
required prior to drilling.
On October 27 and 28, 2005, Stewart Environmental, with drilling assistance from
Aspen
Environmental, advanced three soil borings (3-5, 3-6, and 3-7) and installed
six monitoring wells
(MW-I through MW-6) in the
vicinity of the previously identified contaminated B-I borehole.
Boring and well locations are shown on Figure 2.
Boring and well locations were established using a modified version of the
45-Degree “Step Out” Technique for sampling, allowing for the building adjacent
to B-l. The six monitoring wells consisted of these nested pairs (MW-I and 2,
MW-3 and 4, and MW-S and 6). Wells MW-I, MW- 3, and MW-S were installed to a
depth of 6 feet below ground surface (bgs) and wells MW-2, MW-4, and MW-6 were
installed to a depth of 16 feet bgs, the depth at which weathered bedrock was
encountered. Drilling refusal occurred at approximately 19 feet bgs; solid
bedrock appeared to be at 18.5 to 19 feet bgs.
The rationale for installing nested wells and at the previously referenced
depths is as follows. Onsite groundwater is very shallow, approximately 3 feet bgs. The 6-foot deep monitoring wells were
slotted from 2 feet to 5 feet bgs to collect potential contaminants with
specific gravities less than that of water (floaters). The 16-foot wells were
slotted from 14 feet to 16 feet bgs to collect potential contaminants with
specific gravities greater than that of water (sinkers). Well logs indicate
that a confining layer does not exist between groundwater surface and top of
bedrock; soils consisted of clayey sands, sandy clays, and sand with gravel.
Therefore, it is thought that a continuous water column exists between
approximately 3 feet bgs and bedrock depth and that more than one discreet
aquifer does not exist at the site.
The three boreholes (3-5, B-6, and 13-7) were installed to delineate horizontal
and vertical soil contamination as well as groundwater contamination. Drilling
was completed with a Geoprobe rig, using standard U.S. Environmental Protection
Agency (EPA) sampling and decontamination protocol. The three borings were
advanced to approximately 19 feet bgs, the depth at which drill refusal
occurred. Continuous soil cores were collected from the borings. The core
samples were screened in the field for volatile vapors with a photoionization
detector (PID). At Borings B-S and B-6, soil cores appeared clean; therefore,
one soil sample was selected from each core at the approximate groundwater/soil
interface depth. Boring B-7 was advanced near the known contaminated B-I
Boring. B-7 soil samples were collected at two
depths, one in the area of what appeared to be
maximum contamination based on field screening and one at a depth below that
where soils appeared clean. The purpose of collecting the lower sample was to
delineate the vertical extent of contamination. One groundwater sample was
collected from each boring. Samples were stored in an ice-filled cooler and
delivered to Stewart Environmental’s laboratory under standard chain-of-custody
protocol. Borehole soil and groundwater samples were collected on October 27,
2005, the day the boreholes were advanced.
The six monitoring wells were installed to delineate aerial extent of
groundwater contamination. Groundwater samples were collected from the six
monitoring wells on October 28, 2005, the day after the wells were installed.
Standard EPA sampling and decontamination protocol were observed. Samples were
stored in an ice-filled cooler and delivered to Stewart Environmental’s
laboratory under standard chain-of-custody protocol.
3554-001(2) Site
Characterization Investigation Page 2 of 8
Community Airpark Association, Inc.
Fort Collins, Colorado
Stewart
Environmental Consultants Inc.