Preliminary Geotechnical Subsurface Exploration And Limited Geologic Study Proposed Airpark Village Fort Collins, Colorado

Prepared for:

Airpark Village, LLC
10763 East Mexico Avenue
Aurora, Colorado 80012

Attention: Mr. Lloyd Goff

Job Number 04-3334 October 8, 2004

ENGINEERING CONSULTANTS
41 Inverness Drive East, Englewood, CO 80112-5412       
Phone (303) 289-1989   
Fax (303) 289-1686       
www.groundeng.com

Office Locations:           
Englewood
Commerce City 
Loveland
Granby
Glenwood Springs

CONCLUSIONS

The subsurface conditions encountered in the test holes generally consisted of a layer of topsoil/organics/vegetation or asphalt pavement, approximately 2 to 5 inches thick, overlying sands, clays, and gravels. These materials were underlain by claystone bedrock that extended to the test hole termination depths at approximately 20 to 35 feet, below existing grades. Groundwater was encountered at the time of drilling at depths of approximately 2 to 7 feet below existing grades and at depths of approximately 2 to 5 feet below grade when measured on September 28, 2004. Water levels will fluctuate, however, in response to annual and longer-term cycles of precipitation, irrigation, surface drainage, land use, and the development of transient, perched water conditions.

Shallow groundwater and a historic collapsible soils/sinkhole-type condition are present at the site. Specific design considerations will be necessary in order to accommodate development. These may include regional drainage/diversionary improvements, extensive overexcavation and processing of the subsurface soils, and raising of site grades by several feet. Site improvements such as infrastructure may be difficult and time intensive to install due to potential dewatering, unstable trench slopes, and saturated soil conditions.

Based on the subsurface conditions encountered in the test holes, the results of our field exploration and laboratory studies, and common, generally accepted design procedures utilized in the northern Front Range area, we anticipate that the majority of the structures at the proposed development could be founded on shallow foundation systems. Floor systems could consist of slab-on-grade construction placed on a layer of properly moisture-density treated, on-site generated or approved import fill materials. This assumes that proper pad preparation possibly including overexcavation and replacement, surcharging and settlement monitoring, and/or significant raising of site grades, as discussed below, is performed as necessary once final recommendations are developed. Depending on final site grading, site-specific exploration, and building specific movement tolerances, some of the structures may require deep foundation/floor systems.

We anticipate pavement sections may consist of a full depth asphalt section of approximately 5 to 7 inches in private paved areas, such as parking and internal drives, and approximately 9 to 11 inches in public roadways, depending upon final roadway classifications. A minimum section of 6 to 7 inches of Portland cement concrete in areas of high truck traffic/concentrated turning movements such as dumpster pads and loading/unloading areas (private) may also be necessary. Pavement subgrade materials will need to be properly moisture-density treated.

These recommendations are presented without the aid of a detailed final site grading plan as well as a detailed final development plan, which were not available at the time of this report preparation. To increase efficiency during the construction process, site grading should be carefully planned to take into consideration the preliminary foundation, floor system, and pavement design recommendations as presented in this report. Properly placed fill materials may significantly reduce the potential of structure, exterior flatwork, and pavement section movements.

Additional preliminary recommendations with respect to foundations, floor systems, site grading, water-soluble sulfates, surface drainage, geologic concerns, and pavement design are contained herein.

PURPOSE AND SCOPE OF STUDY

This report presents the results of a geotechnical evaluation performed by GROUND Engineering Consultants, Inc. (GROUND) to provide preliminary geotechnical recommendations for the proposed Airpark Village development to be located in Fort Collins, Colorado. The project site is located near the intersection of Airway Avenue and East Lincoln Avenue (See Figure 1). Our study was conducted in general accordance with GROUND's Proposal No. 0407-1105 (revised), dated August 25, 2004.

Field and office studies provided information regarding surface and subsurface conditions, including existing site vicinity improvements and depths to bedrock and groundwater. Material samples retrieved during the subsurface exploration were tested in our laboratory to assess the engineering characteristics of the site earth materials, and assist in the development of our preliminary geotechnical recommendations. Results of the field, office, and laboratory studies are presented below.

This report has been prepared to summarize the data obtained and to present our conclusions and preliminary recommendations based on the anticipated construction and the subsurface conditions encountered. Preliminary design parameters and a discussion of geotechnical engineering considerations related to construction considerations for the proposed development are included. When final structure locations and dimensions are known, lot/parcel-specific final geotechnical subsurface exploration programs must be performed in order to confirm the preliminary recommendations provided as well as to provide additional, detailed, building/parcel-specific design information. Additionally, detailed subsurface explorations will be necessary in order to provide pavement design recommendations for the private paved areas upon completion of near final site grading. This report should not be used for detailed design purposes.

PROPOSED CONSTRUCTION

We understand that proposed construction at the site may ultimately include mixed-usage buildings generally consisting of residential, retail, and commercial development that may include two-story residential structures and three-story retail/office buildings. Associated public roadways, private access drives, and parking areas are also planned. In addition, we assume that the proposed construction will consist of extensive overlot grading and installation of underground utilities. As stated, at the time of this report preparation, detailed development plans, final site grading plans, and final building layouts and roadway construction details were not available for our review; however, based on observations conducted in the field and preliminary site grading information provided by the Client, we estimate that cuts and fills across the site will generally be on the order of 10 to 20 feet. Greater cuts and fills may be necessary. If the proposed project, including the anticipated site grading, is significantly different from that described above, GROUND should be notified to re-evaluate the preliminary recommendations in this report.

SITE CONDITIONS

At the time of our exploration, the site generally existed as the Fort Collins Downtown Airport and vacant pasture land. Vegetation consisted of short to medium grasses and weeds and sparsely located deciduous trees. The general topography of the site is gently rolling with slopes up to 3 percent descending towards the southeast. The site varies in elevation from approximately 4,918 to 4,940 feet msl. The site is bordered by commercial development to the south and southwest, residential development and International Boulevard to the north, and commercial development and Timberline Road to the east. The airport terminal, runway, and hangars, along with asphalt and concrete

pavement parking are located along the southern border of the site. Indications of underground utilities were also observed at the project site. It should be noted that a drainage pond is located near the eastern perimeter of the site, just east of Test Hole 19. Flowing water was observed entering this pond through a pipe that appears to extend to the northwest an unknown distance (see pictures in Appendix). Additionally, Dry Creek traverses the approximate center of the site.

Based on GROUND's visits to the site, we observed localized sinkhole development within various areas of the site. In particular, two significant sinkholes were observed immediately adjacent to the west of the Valley Air Service maintenance building as well as in numerous other locations within paved areas surrounding the airport terminal. This condition is discussed in greater detail in latter sections of this report.

GEOLOGIC SETTING

The subject parcel lies within the Denver Basin geologic province that consists largely of a sequence of sedimentary rock formations deposited and preserved in a structural depression in north-central Colorado. In the general project area, these sedimentary rocks dip eastward at low angles (less than 10 degrees, typically) and are overlain by a variety of surficial deposits including alluvial (stream-laid) sediments, eolian (wind-blown) materials and colluvial (slope-wash) deposits.

The site is mapped as underlain by Middle to Upper Pleistocene to Holocene alluvial soils associated with the Cache la Poudre River and its tributaries. The unconsolidated materials are depicted as underlain by interbedded strata of the upper member of the Cretaceous Pierre Shale formation. In the Colorado Front Range area, the Pierre Shale consists largely of clay shales and claystones with local, interbedded sandstones. The shales and claystones typically are moderately to highly expansive.

GEOLOGIC HAZARDS


Expansive Soils
The shallow earth materials underlying the site include clay shales and claystones. Swelling clayey soils and bedrock change volume in response to changes in moisture content that can occur seasonally, or in response to changes in land use, including development. Expansion potentials vary with moisture contents, density and details of the clay chemistry and mineralogy. The swell potential in any particular area can vary markedly both laterally and vertically due to the complex interbedding of the site soil and bedrock materials. Moisture changes also occur erratically, resulting in conditions that cannot always be predicted.

Swell-consolidation testing of samples of the Pierre Shale indicated negligible to low potentials for heave (See Table 1). Although there is a significant amount of risk involved where structures are placed directly on these types of materials, the depth of non-expansive sands and gravels overlying the bedrock materials together with the shallow water table at the site significantly reduces the risk of soil expansion adversely affecting the site. It is important, however, that the soil conditions be reviewed on an individual structure basis when site building layouts are known.

Collapsible Soils Certain surficial deposits in the Front Range area are known to be susceptible to local hydro-consolidation or "collapse." Hydro-consolidation consists of a significant volume loss due to re-structuring of the constituent grains of the soil to a more compact arrangement upon wetting.

Portions of the site upper surficial soils are interpreted to have collapsible soil potential. The index parameters for site soils assessed for this study, did fall into the range typically associated with collapsible soils (e.g. Naval Facilities Engineering Command, 1986). Therefore, the likelihood of encountering collapsible soils on the subject site is considered high. The following observations with regard to collapsible soils were observed onsite during the site reconnaissance.

•           Conical depressions in the native materials were observed across the site as shown in Photographs 3 and 4 contained in Appendix A. The conical depressions are variable in dimension with diameter ranging from 3 to 10 feet with depths ranging from 1 to 3 feet below existing grades.

•           Portions of the existing paved runway for the site are experiencing and have experienced over the past 30 years severe pavement distress and pavement failure as a result of piping failure of surficial soils as shown in photographs in 5 and 6 contained in Appendix A.

•           Existing buildings at the site area have experienced foundation distress, and pavement failure as a result of piping failure of surficial soils as shown in photographs in 7 and 8 contained in Appendix A.

Additional geotechnical evaluations of the subject site must address the potential of consolidation in the foundation soils, so that appropriate, remedial design and construction can be implemented, if necessary.

Radon Testing for the possible presence of radon gas prior to project development does not yield useful results regarding the potential accumulation of radon in completed structures. Radon accumulations most typically are found in basements or other enclosed portions of buildings built in areas underlain at relatively shallow depths by granitic crystalline rock. The likelihood of encountering radon in concentrations exceeding applicable health standards on the subject site, underlain by relatively deep soils and sedimentary bedrock, is significantly lower.

GROUND recommends that radon testing be performed in each building on-site, after construction is completed. Proper ventilation usually is sufficient to mitigate potential radon accumulations. Building designs should accommodate such ventilation for all building areas.

Seismic ActivitylFaulting Neither site reconnaissance nor review of available geologic maps indicated the trace of an active or potentially active fault traversing or immediately adjacent to the site. Therefore, the likelihood of surface fault rupture at the site is considered to be low.

The closest documented active fault to the site is the Rocky Mountain Arsenal Fault, which is located approximately 40 miles to the south (Kirkham and Rogers, 1981). This fault is approximately 15 miles in length, trends generally northwest/southeast and is considered to be a right-lateral, strike-slip fault. The most recent significant seismic movements associated with the fault occurred in the 1960's, generating earthquakes up to magnitude 5.5. Research performed by the U.S. Geological Survey concluded that a strong correlation existed between the seismic activity of this fault and pressure injection of liquid waste into a disposal well located at the nearby Rocky Mountain Arsenal. Pressure injection in the disposal well was discontinued in 1966 and only minor seismic activity along the fault has been recorded since. The risk of this fault giving rise to damaging, earthquake-induced ground motions at the site is considered to be relatively low given the low previously recorded seismic magnitudes.

 

 

 

Other faults mapped as `potentially active' are located in the Rocky Mountains to the west and northwest of the site. As `potentially active' faults, they constitute at lower risk in comparison to active faults.

The project area falls within Seismic Performance Category A based on AASHTO guidelines, and is considered to have a low probability for large, damaging earthquakes. The site is in the Uniform Building Code Seismic Zone 1, although the Colorado Geological Survey recommends that building design following the guidelines for Zone 2 be considered. Compared with other regions of Colorado, recorded earthquake frequency in the project area is low.

Slope Stability and Erosion As noted in the "Site Conditions" section of this report, the site is relatively flat to gently sloping. During our preliminary reconnaissance of the site area, no evidence was noted of mass-wasting processes associated with steep slopes, such as landslides, slumps or unusual soil creep. Therefore, the likelihood of project developments being affected by large scale, unanticipated slope instabilities is considered low.

Preliminarily, we recommend that un-retained, permanent slope cuts be less than 10 feet in height and maintain a maximum 3:1 (horizontal : vertical) slope angle or less with proper erosion control measures implemented. Proper surface drainage controls to reduce the potential for erosional slope damage need to be implemented in the grading design to control runoff, which may be increased due to proposed pavement surfaces, structures and landscape irrigation. Re-vegetation or other means of protection should be used on graded slopes.

Flooding The subject property lies near Dry Creek about 1,500 feet from the Cache La Poudre River. The groundwater table is quite shallow. Significant fluctuation in the flow of these drainages can be expected seasonally. In addition, local, surface saturation may result during episodes of heavy rainfall and associated temporary ponding of run-off in areas of relatively slow surface drainage.

Wetlands Potential No surface water, typical phreatophytes or other indications of conditions similar to jurisdictional wetlands were apparent on the site during GROUND's site reconnaissance with the exception of the drainage pond located near the eastern perimeter of the site. However, during site development all regulations concerning

wetland protection, as well as any other areas designated as wetlands by the Federal Wetlands Protection Act should be adhered to. Explicit designation of wetlands was not included as part of the scope of this study, and relatively shallow groundwater exists site wide,

Mining Activity and Subsidence Review of U.S. Geological Survey topographic maps covering the site (e.g., U.S.G.S. 1960, revised 1984) and Jones, and others (1978) and other available, published maps depicting areas of coal extraction, did not indicate past mining activities on or adjacent to the subject parcel. No indications of mining activities were apparent on the site during the site reconnaissance. Therefore, there appears to be little potential for surface subsidence associated with consolidation of former mine workings at depth.

Published geologic maps do not indicate formations underlying the site at shallow depths that include evaporite (salt, gypsum, etc.) deposits, limestones or other materials vulnerable to subsurface dissolution. Therefore, the likelihood of subsidence or other mining-related hazards appears to be low.

Based on the published information reviewed for the site and the findings of this preliminary assessment, the site generally appears to be feasible for development with respect to potential geologic hazards, provided appropriate geotechnical and civil design are implemented to reduce the potential of ongoing, continued collapse of surficial soils on the site to an acceptable level.

SUBSURFACE EXPLORATION

The subsurface exploration for the project was conducted September 20 through September 22, 2004. A total of twenty-three (23) test holes were drilled with a track-mounted, continuous flight power auger rig to evaluate the subsurface conditions as well as to retrieve soil and bedrock samples for laboratory testing and analysis. The test holes were drilled at the approximate locations as indicated in Figure 1. Temporary piezometers were installed to a depth of approximately 10 feet below the existing grade in eleven (11) of the test holes to measure water levels. A representative of GROUND directed the subsurface exploration, logged the test holes in the field, and prepared the soil samples for transport to our laboratory.

Samples of the subsurface materials were taken with a 2-inch I.D. California liner sampler. The sampler was driven into the substrata with blows from a 140-pound hammer falling 30 inches. This procedure is similar to the Standard Penetration Test described by ASTM Method D1586. Penetration resistance values when properly evaluated indicate the relative density or consistency of the soils and bedrock. In addition, large disturbed samples were obtained from the auger cuttings for laboratory compaction testing (the "standard Proctor"). Depths at which the samples were obtained and associated penetration resistance values are shown on the test hole logs.

The approximate locations of the test holes are shown in Figure 1. Logs of the exploratory test holes are presented in Figures 2 through 6. Explanatory notes and a legend are provided in Figure 7.

LABORATORY TESTING
Samples retrieved from our test holes were examined and visually classified in the laboratory by the project engineer. Laboratory testing of soil and bedrock samples obtained from the subject site included standard property tests, such as natural moisture contents, dry unit weights, grain size analyses, and liquid and plastic limits. Swell-consolidation potential and water-soluble sulfate contents were determined for selected samples, as well. Compaction tests were performed on the representative composite bulk samples. Laboratory tests were performed in general accordance with applicable ASTM and AASHTO protocols.

Results of the laboratory testing program are summarized on Table 1
e

SUBSURFACE CONDITIONS

The subsurface conditions encountered in the test holes generally consisted of a layer of topsoil/organics/vegetation or asphalt pavement, approximately 2 to 5 inches thick, overlying sands, clays, and gravels. These materials were underlain by claystone bedrock that extended to the test hole termination depths at approximately 20 to 35 feet, below existing grades. Groundwater was encountered at the time of drilling at depths of approximately 2 to 7 feet below existing grades and at depths of approximately 2 to 5 feet below grade when measured on September 28, 2004. Water levels will fluctuate, however, in response to annual and longer-term cycles of precipitation, irrigation, surface drainage, land use, and the development of transient, perched water conditions.

Sands andlor clays were observed in each of the test holes. The sands and clays were often silty, fine to coarse grained with occasional gravels, non-plastic to highly plastic, very soft to very stiff (very loose to medium dense), moist to wet, brown in color, and occasionally calcareous.

Sands and gravels were also observed in each of the test holes. The sands and gravels were medium to coarse grained, non-plastic to low plastic, medium dense to dense, moist to wet, and brown in color.

Claystone bedrock was also observed in each of the test holes. The bedrock was fine to medium grained, medium to highly plastic, medium hard to very hard, slightly moist to moist, and gray to dark gray in color.

Swell-consolidation testing suggested a negligible to low potential for heave and consolidation in the on-site soils and bedrock. Swells ranging from 0.3 to 0.9 percent and consolidations ranging from 0.1 to 0.3 percent were measured upon wetting under a 1,000 psf surcharge pressure. Potential for consolidation related to the sinkhole condition is high without significant grading or other mitigative efforts. Higher swell potentials may be present at the project site.

COLLASPSIBLE SOILS CONSIDERATIONS
As referenced in the Collapsible Soils section of this report, the sand and clay soils encountered in the upper 5 to 10 feet of surficial overburden materials across the site have a potential for collapse. These materials typically have a low in-place density and high moisture content. Recommendations to reduce the potential of collapsing soil affecting new development are addressed in the Site Grading portion of this report.

GROUNDWATER CONSIDERATIONS
As mentioned throughout this report, shallow groundwater is present at the project site and was encountered at the time of drilling and when checked soon after, at depths of approximately 2 to 7 feet below existing grades. It has been GROUND's experience that for many smaller sized developments, where localized shallow groundwater is encountered, water infiltration can often be effectively reduced through proper drainage design including raising structure grades, the use of perimeter drain and underdrain systems, pumps, detention ponds, channels, etc. However, within the project site, groundwater does not appear to be localized; rather it is GROUND's opinion that this condition is most likely regional, i.e., extends beyond the perimeter of the site for a significant distance. Therefore, the groundwater condition may require a substantial diversionary system rather than commonly utilized surface and shallow subsurface drainage methods. Often, these extensive regional drainage improvements may be detrimental to upgradient and downgradient areas and may not be financially feasible for projects of this size. Therefore, it is common practice to raise site grades creating a separation between structural elements and the groundwater. We would estimate the site to be raised approximately 5 to 8 feet or more from existing grades in order to obtain an adequate separation. Specific site evaluations will be necessary to further address this option.

As a result of the groundwater condition at the site, the construction of basements or other below-grade levels may also not be feasible. In the event roadways and other at-grade elements are not raised from the existing grades, overexcavation of subgrade materials and dewatering during construction will likely be required in order to obtain satisfactory compaction.

Site soils excavated in their current state may not meet the moisture-density requirements specified in latter sections of this report due to moisture contents above optimum as well as saturation. In order to use these materials with high to very high moisture contents, extensive processing to "dry" and mix them, subsequently creating a homogenous and consistent material, will be required. In the event these materials cannot be processed correctly, import fill materials may be necessary.

In addition, utility installation may be difficult due to the presence of shallow groundwater. Properly designed and installed dewatering systems may be required during construction within trenches. The risk of slope instability will be significantly increased in areas of seepage along excavation slopes. Should site constraints prohibit the use of recommended slope angles, temporary shoring should be used.

GROUND would encourage the Client to consult with a Civil Engineer specializing in water modeling and detailed drainage design to further evaluate the surface and subsurface water conditions and its impact on the desired development.

SITE GRADING

A detailed final site grading plan was not available at the time of this report preparation. Based on observations conducted in the field and preliminary site grading information provided by the Client, we estimate that cuts and fills across the site will generally be on the order of 10 to 20 feet. Greater cuts and fills may be necessary. Due to the collapsible nature of the surficial soils and shallow groundwater conditions at the project site, detailed site grading recommendations will need to be developed.

Based on the previous site history of collapsing soils and groundwater occurring at or above existing site grades, it appears that an import of offsite granular materials placed in a properly moisture-density treated state will be required to raise overall grades of the site to allow for future development. The final finished grade for the site-specific proposed structures and flatwork areas will be dependent upon a drainage study by a civil engineer.

Site grading options for consideration to achieve this goal are as follows.

1.  Partial removal and replacement or mixing of the underlying surficial collapsible soils with properly compacted imported granular fill materials.
2. Densification of collapsible soils inplace by methods such as surcharge or dynamic compaction with subsequent placement of overlying properly compacted imported granular fill materials.

GROUND recommends consultation with other Project Team members with regard to site grading options once a review of proposed drainage improvements has been performed. Therefore, the information presented in this section should be utilized solely as a guideline for preliminary design purposes.

Site grading should be carefully planned to take into consideration the preliminary recommendations regarding foundation and floor systems as presented in this report. Site grading should be planned carefully to provide positive surface drainage away from buildings, and all pavements, utility alignments, and flatwork. Surface diversion features should be provided around paved areas to prevent surface runoff from flowing across the paved surfaces.

Site soils free of deleterious materials are generally suitable for placement as compacted fill. Claystone fragments larger than 2 inches and cobbles larger than 6 inches should not be incorporated into project fills. Care should be taken, however, with regard to achieving and maintaining proper moisture contents during placement and compaction. We anticipate that a high percentage of the on-site soils may exhibit significant pumping, rutting, and deflection at moisture contents near optimum and above.

Following the development of site-specific grading and additional site-specific subsurface exploration, the placement of on-site fill materials should be monitored by a representative of GROUND. Quality control testing including nuclear density methods should be conducted in order to ensure proper placement.

Prior to earthwork construction, existing vegetation, topsoil, and other deleterious materials should be removed and disposed of off-site. Relic underground utilities, if encountered should be abandoned in accordance with applicable regulations, removed as necessary, and capped at the margins of the property. Based on conversations with the airport staff, various deleterious/uncontrolled materials have been placed in the locations of previous "sinkholes" including but not limited to concrete block, asphalt, gravel, and sand. Any deleterious materials should be removed in their entirety and replaced with moisture-density treated onsite-generated or approved import till materials. Remnant foundation elements and all construction debris generated as a result of the demolition of the on-site structures should be entirely removed and the resultant excavations properly backfilled. The Geotechnical Engineer should test the excavation backfill during placement.

Topsoil should not be incorporated into common fill placed on the site. Instead, topsoil should be stockpiled during initial grading operations for placement in areas to be landscaped or for other approved uses. If surfaces to receive fill expose loose, wet, soft or otherwise deleterious material, additional material should be excavated or other measures taken, to establish a firm platform for filling.

During planning for site grading, the Owner should consider utilizing granular or overburden materials in structure areas and placing claystone materials in lower fill zones in non-building areas if possible.

Settlements will occur in filled ground, typically on the order of 1 to 2 percent of the fill depth. If fill placement is performed properly and is tightly controlled, in GROUND's experience approximately 70 percent of that settlement will take place during earthwork construction. The remaining potential settlement likely will take 1 to 3 years, or longer, to be realized.

No fill materials should be placed, worked, rolled while they are frozen, thawing, or during poor/inclement weather conditions. Care should be taken to place all fills in a controlled state. In the event that proper moisture and compaction is not achieved, the potential for structural movement, related to differential settlement, greatly increases. The Geotechnical Engineer should observe the exposed excavation surface prior to placement of fill, and observe earthwork operations and test the soils.

Potential earthwork contractors should be made aware that significant processing and reprocessing of the on-site materials may be required. The placement of on-site fill materials should be monitored on a full-time basis by a representative of the Geotechnical Engineer. Quality control testing should be conducted at an increased frequency in order to ensure proper placement.

Permanent site slopes supported by on-site soils up to 10 feet in height should be constructed no steeper than 3:1 (horizontal : vertical). Minor raveling or surficial sloughing should be anticipated on slopes cut at this angle until vegetation is well re-established. Surface drainage should be designed to direct water away from slope faces.

ANTICIPATED FOUNDATION/FLOOR SYSTEMS
Based on the subsurface conditions encountered in the test holes, the results of our field and laboratory studies, and the nature of the proposed construction, we believe the proposed structures could be founded on a shallow foundation system, constructed on either properly moisture-density treated, on-site materials, exclusive of claystone bedrock or approved import fill materials. This assumes that proper pad preparation possibly including overexcavation and replacement, surcharging and settlement monitoring, and/or significant raising of site grades, if so required, is performed once final recommendations are developed. GROUND anticipates that shallow foundation systems may be designed for an allowable soil bearing pressure of 1,500 psf to 3,000 psf, based on final site grades and man-made fill depths. Additionally, due to the presence of relatively shallow groundwater across the site, the potential for water infiltration beneath structural elements should be addressed during preliminary developmental layout.

Depending on final site grading, site-specific exploration, and building specific movement tolerances, some of the structures may require deep foundation systems. Potential foundation systems may include drilled piers or driven piles. Driven piles may prove to more cost effective due to the granular nature and caving potential of the overburden materials, along with the shallow groundwater depths encountered at the site.

The on-site soils, exclusive of topsoil and any deleterious materials, may be suitable to support lightly to moderately loaded slab-on-grade construction following additional exploration, evaluation, and development of site specific recommendations. As stated above, overexcavation and replacement with properly processed on-site materials or import structural fill materials may also be deemed necessary. Proposed building structures having tight tolerances for post-construction movements may require the use of structural floor systems. Site specific conditions will need to be identified in order to provide final recommendations.

WATER-SOLUBLE SULFATES AND CORROSIVITY

The concentrations of water-soluble sulfates measured in selected samples obtained from the test holes ranged from 0.70 percent up to 1.00 percent by weight. Such concentrations of water-soluble sulfates represent a severe environment for sulfate attack on concrete exposed to these materials. Degrees of attack are based on the scale of 'negligible,' 'moderate,' 'severe' and 'very severe' as described in the "Design and Control of Concrete Mixtures," published by the Portland Cement Association (PCA).

Based on these data and PCA and Colorado Department of Transportation (CDOT) guidelines, GROUND preliminarily recommends the use of sulfate-resistant cement in all concrete exposed to site soils, conforming to one of the following requirements:

1)  Type V, as specified by ASTM C150.
2)  Type II with a maximum CM content of 5 percent and a maximum content of (C4AF + 2[C3A]) of 25 percent.
3)  Type II or Type I/ll and 15 to 20 percent of the cement shall be replaced with an approved Type F fly ash.
4)  A blended cement conforming to Type HS, as specified by ASTM C1157.

Other cement types or blends may be acceptable, however, if type-specific test data demonstrate equal or superior sulfate-resistance to Type V cement. Test data should be provided to the Geotechnical Engineer for review, and the cement approved, prior to use. All concrete used should have a maximum water/cement ratio of 0.45 by weight. All concrete exposed to site soils should have a minimum compressive strength of 4,250 psi. Concrete mixes should be relatively rich and should be air entrained. Additional sampling and testing should be performed in order to confirm these preliminary findings.

Data was collected to determine the potential corrosive environment for metal placed beneath the ground surface. The testing included pH determination and electrical resistivity measurements. Test results are summarized on Table 1. The acidity of the subsurface materials was assessed by conducting pH tests on samples of the on-site soils. The pH test results indicated values ranging from approximately 7.4 to 8.0, which indicate that the materials are slightly basic. These characteristics will not contribute greatly to corrosion.

Electrical resistivity measurements conducted on samples of the overburden soils indicate resistivity values ranging from 427 to 1,358 ohm-centimeters. Electrical resistance is related to moisture content and the quantity of dissolved salts and other deteriorative compounds in the soil. Soil resistivities between 0 and 2,000 ohm-centimeters are classified as having a `bad' corrosive resistance, as presented in the "Handbook of Steel Drainage and Highway Construction Products" published by the American Iron and Steel Institute. We recommend a qualified corrosion engineer review the information to design an appropriate level of corrosion protection for buried metal at the project site.

UTILITY AND EXCAVATION RECOMMENDATIONS

On-site soils and bedrock excavated from trenches may be suitable for use as trench backfill, provided they are processed properly. Additional subsurface exploration should be performed within utility alignments to further evaluate potentially encountered subsurface conditions.

The test holes for the subsurface exploration were excavated to the depths indicated by means of track-mounted, flight auger drilling equipment. We anticipate no significant excavation difficulties in the majority of the site with conventional heavy-duty excavation equipment in good working condition. Depending on final site grading plans, equipment with large ripper teeth may be required in order to adequately remove and assist in properly placing fill materials.

We preliminarily recommend temporary excavation slopes up to 5 feet deep not steeper than a ratio of 1.5 (H) to 1 (V) in the on-site soils and 3/ (H) to 1 (V) in the native soils. Some surface sloughing may occur on the slope faces at these angles.

Should site constraints prohibit the use of the recommended slope angles, temporary shoring should be used. The shoring should be designed to resist the lateral earth pressure exerted by building, traffic, equipment, and stockpiles. GROUND can provide shoring design upon request.

Groundwater was encountered in the test holes at depths of approximately 2 to 7 below existing grades during our subsurface exploration and at depths of approximately 2 to 5 feet below grade when measured on September 28, 2004. However, local perched water conditions may develop at shallower depths as stated in various sections of this report resulting in significant seepage in excavations.

Good surface drainage should be provided around temporary excavation slopes to direct surface runoff away from the slope faces. A properly designed swale should be provided at the top of the excavations. In no case should water be allowed to pond at the site. Slopes should be protected against erosion. Erosion along the slopes will result in sloughing and could lead to a slope failure. Any excavations in which personnel will be working must comply with all OSHA Standards and Regulations (CFR 29 Part 1926). The Contractor's "responsible person" should evaluate the soil exposed in the excavations as part of the contractor's safety procedures. GROUND is providing this information solely as a service to the Client and is not assuming responsibility for construction site safety or the contractor's activities.

SURFACE DRAINAGE RECOMMENDATIONS

The following drainage precautions should be taken into consideration during design of the proposed development,

1)  Wetting or drying of the foundation excavations and underslab areas should be avoided during and after construction as well as throughout the life of the facilities. Permitting increases/variations in moisture to the supporting soils may result in a decrease in bearing capacity and an increase in settlement, heave, and/or differential movement.

2)  Positive surface drainage measures should be provided and maintained to reduce water infiltration into foundation soils. The ground surface surrounding proposed building exteriors should be sloped to drain away from the foundation in all directions. We recommend a minimum slope of 12 inches in the first 10 feet in the areas not covered with pavement or concrete slabs, or a minimum 3 percent in the first 10 feet in the areas covered with pavement or concrete slabs. In no case should water be allowed to pond near or adjacent to foundation elements.  Drainage measures also should be included in project design to direct water away from sidewalks and other hardscaping as well as utility trench alignments which are likely to be adversely affected by moisture-volume changes in the underlying soils or flow of infiltrating water.

3)  Roof downspouts and drains should discharge well beyond the perimeters of the structure foundations, or be provided with positive conveyance off-site for collected waters.

4)  Landscaping which requires watering should be located 10 or more feet from building perimeters. Irrigation sprinkler heads should be deployed so that applied water is not introduced into foundation soils. Landscape irrigation should be limited to the minimum quantities necessary to sustain healthy plant growth.  Use of drip irrigation systems can be beneficial for reducing over-spray beyond planters. Drip irrigation can also be beneficial for reducing the amounts of water introduced to building foundation soils, but only if the total volumes of applied water are controlled with regard to limiting that introduction. Controlling rates of moisture increase beneath the foundations and floors should take higher priority than minimizing landscape plant losses.  Where plantings are deemed absolutely necessary within 10 feet of a building, GROUND recommends that the plants be placed in water-tight planters, constructed either in-ground or above-grade, to reduce moisture infiltration in the surrounding subgrade soils. Planters should be provided with positive drainage and landscape underdrains.

5)  Plastic membranes should not be used to cover the ground surface adjacent to foundation walls. Perforated "weed barrier" membranes that allow ready evaporation from the underlying soils may be used.

PRELIMINARY PAVEMENT SECTIONS

A pavement section is a layered system designed to distribute concentrated traffic loads to the subgrade. Performance of the pavement structure is directly related to the physical properties of the subgrade soils and traffic loadings. The standard care of practice in pavement design describes the recommended flexible pavement section as a "20-year" design pavement. However, most flexible pavements will not remain in satisfactory condition without routine maintenance and rehabilitation procedures performed throughout the life of the pavement.

We anticipate pavement sections may consist of a full depth asphalt section of approximately 5 to 7 inches in private paved areas such as parking and internal drives and approximately 9 to 11 inches in public roadways, depending upon final roadway classification. A minimum section of 8 to 7 inches of Portland cement concrete in areas of high truck traffic/concentrated turning movements such as dumpster pads and load ingJunloading areas (private) may also be necessary. Pavement subgrade materials will need to be properly moisture-density treated.

The collection and diversion of surface drainage away from paved areas is extremely important to satisfactory performance of the pavements. The subsurface and surface drainage systems should be carefully designed to ensure removal of the water from paved areas and subgrade soils. Allowing surface waters to pond on pavements will cause premature pavement deterioration. Where topography, site constraints, or other factors limit or preclude adequate surface drainage, pavements should be provided with edge drains to reduce loss of subgrade support. The long-term performance of the pavement also can be improved greatly by proper backfilling and compaction behind curbs, gutters, and sidewalks so that ponding is not permitted and water infiltration is reduced.

ADDITIONAL EXPLORATION REQUIREMENTS

The above data and recommendations are based on a limited preliminary subsurface exploration only. Additional geotechnical studies must be performed to further evaluate the site for site-specific foundation and floor system recommendations, final site grading and pavement recommendations.

CLOSURE
Geotechnical Review

The poor performance of many pavements, foundations, and subsurface structures has been directly attributed to inadequate geotechnical review and earthwork quality control. Therefore, project plans and specifications should be reviewed by the Geotechnical Engineer to evaluate whether they comply with the intent of the recommendations in this report. This review should be reported in writing.

In addition, building-specific geotechnical exploration(s) must be completed for the project prior to final design and construction. The preliminary geotechnical recommendations presented in this report are highly contingent upon the completion of final geotechnical studies as well as construction observation and materials testing of project earthworks by representatives of GROUND. If another geotechnical consultant is selected to provide these services, then that consultant must assume all responsibility for the geotechnical aspects of the project by concurring in writing with the recommendations in this report, or by providing alternative recommendations.

Limitations

This report has been prepared for Airpark Village, LLC as it pertains to design of the proposed multi-use development as described herein. It may not contain sufficient information for other parties or other purposes. In addition, GROUND has assumed that the final geotechnical subsurface exploration will commence by Fall of 2006 or before. Changes in project plan development or schedule should be brought to the attention of the Geotechnical Engineer, in order that the preliminary geotechnical recommendations may be re-evaluated and, as necessary, modified.

The preliminary geotechnical conclusions and recommendations in this report relied upon subsurface exploration at a limited number of exploration points as shown on Figure 1. Subsurface conditions were interpolated between and extrapolated beyond these locations. Findings were dependent on the limited amount of direct evidence obtained at the time of this geotechnical evaluation. Our recommendations were developed for site conditions as described above. Actual conditions exposed during construction may be anticipated to differ, somewhat, from those encountered during site exploration.

The materials present on-site are stable at their natural moisture content, but may shrink, swell, or lose bearing capacity with changes in moisture content. It is the responsibility of the design team (the architect(s), civil engineer(s), landscape architect(s), structural engineer(s), and ownership) as well as the construction and maintenance contractor(s) to ensure that moisture is directed away from site improvements prior to infiltrating the underlying soils.

Performance of the proposed foundation and pavement will depend on implementation of the recommendations in this report and on proper maintenance after construction is completed. Because water is the principal cause of volume change in expansive soils and rock, the design, construction, and maintenance of the improvements must eliminate changes in moisture content of the site soils.

This report was prepared in accordance with generally accepted soil and foundation engineering practice in the Fort Collins, Colorado, area, at the date of preparation. GROUND makes no other warranties, either express or implied, as to the professional data, opinions or recommendations contained herein. Because of numerous considerations, which are beyond GROUND's control, the economic or technical performance of the project cannot be guaranteed in any respect.

We appreciate the opportunity to complete this portion of the proposed Airpark Village development project. GROUND welcomes the opportunity to provide the Owner with proposals for final subsurface exploration programs as well as construction observations and materials testing services prior to the commencement of construction activities.

Please contact us with any questions or if you require additional information.

Sincerely,
GROUND Engineering Consultants, Inc.
Andrea Hornig, EIT
Reviewed by James Kowalsky, P.E.

Phase II Report

Graphics

Area Aerial Photograph

Area Aerial Photograph

Area Aerial Photograph

Drainage pipe in swampy area east of test hole 19

Conical depression area in native materials

Severe pavement distress associated with existing runway

Active piping failure adjacent to existing structure due to increase surface runoff

Summary of lab test results (page1)

Summary of lab test results (page2)

Summary of lab test results (page3)

Log of test holes (page 1)

Log of test holes (page 2)

Test hole log legend